Or just put each other on ignore. Got to drive today as I have to go to Brentwood later, not looking forward to trying to get home from there....might have to overstay my welcome!Less of the bickering. Ruining my awesome moaning thread. PM each other if you want to pull each others pigtails.
Jesus ****ing Christ - not worth trying to enter or leave the boroughs of Southend or Castlepoint all weekend then!Today's Echo says that the A13 between Sadlers and Pitsea on both sides of the road will be closed all next weekend.
If you turn off of Sadlers towards the A127 there is now a "raised road" over the underpass carrying the "sweep" road from the A13 direct. Next weekend is going to be carnage, my other half isn't happy as he is working all next weekend....going up to London at 6 a.m. will probably not be too bad but coming home won't be fun!Which bridge is this ? The one thats going to be the slip road from the A13 heading east to turn off to Benfleet ?
Tonight shall be interesting. Match night and no way of getting to Southend without hitting massive delays.
WIth hindsight I could have got a train in today and probably should have.
Update
Scheme still on programme, opening Spring 2012.
Three remaining bridges, Sadlers Farm Bridge, Sadlers Hall
Bridge and Church Road Bridge, all programmed to open March/ April 2012.
The completion dates for the remaining elements of the programme are as follows:
Church Road Bridge open – 20th April
Northbound Strategic Link open (one lane only) – 21st April
Deconstruction of Old Church Road Bridge – 28th/29th April
Sadlers Farm Bridge open (A13 leading to the Sadlers Farm Roundabout taking traffic over the strategic link) – 5th May
Southbound Strategic Link open – 31st May
Sadlers Farm Roundabout (signals operational) – 31st May.
There will be some final work taking place once the scheme is open to traffic, with all work completed and away from the network by 27th June.